Beach Drive Construction Update No.5
Posted on Monday, July 28, 2025 02:54 PM
Work Completed This Week
- Installation of hoarding fence was completed along Beach Drive, from Spruce Street to 2nd Street
- Watermain work occurred on Main Street to facilitate upcoming pipe works
- Continued removals of existing infrastructure on Beach Drive Crews have installed floating barriers in the river, designed to manage silt and sediment, at the storm outlet.
- Crews started working on the storm outlet at Spruce Street, to then start installing storm pipe
- The dewatering operations continue to...
Beach Drive Construction Update No.4
Posted on Friday, July 18, 2025 02:18 PM
Work Completed This Week Construction Update
- Continued to install hoarding fence along Beach Drive from Spruce Street to 2nd Street
- We continued to remove existing infrastructure on Main Street, Spruce Street and Beach Drive
- Crews began installing the dewatering system and installed dewatering well points to address ground conditions for the upcoming pipe installation
- We installed wayfinding signage on the fence to help residents and visitors navigate to the beach and local businesses
- Infrastructure...
Beach Drive Construction Update No.3
Posted on Thursday, July 17, 2025 03:47 PM
Work Completed This Week Construction Update
- Installation of hoarding fence continued along Beach Drive from Spruce Street to 2nd Street
- Removals of existing infrastructure continued on Main Street and Beach Drive
- Removals began on Spruce Street at Main Street
- Infrastructure Investigation throughout project limits
- Installation of wayfinding signs to help the public identify where they are, beach access points, and businesses open for business.
Working Coming Up Next Week
- Continuation of hoarding fence...
Beach Drive Construction Update No.2
Posted on Friday, July 04, 2025 03:05 PM
Work Completed This Week Construction Update
- Installed traffic control measures and signs. Beach Drive is now closed between Spruce Street and 2nd Street.
- Pedestrian fencing has been installed along Main Street, Beach Drive, and 1st Street. Sidewalks remain open for businesses and beach access.
- Began installing hoarding fence along Beach Drive.
- Started to remove existing infrastructure on Main Street and Beach Drive.
- Continued to move equipment and materials to the site this week.
- Continued...
Beach Drive Construction Update No.1
Posted on Tuesday, June 24, 2025 01:22 PM
Welcome to our first update on Beach Drive construction.
Construction Update
- This week, crews are organizing and moving equipment and materials around, getting ready to put shovels in the ground.
- We’re getting ready to install traffic control and other signage.
- We’re going to be closing Beach Drive between Spruce St. and 2nd Street N.
- We will begin to install hoarding fencing along Beach Drive, and pedestrian fencing of the work area will begin.
- We’re completing infrastructure investigations at Main...